State-owned construction company, PT Waskita Karya Tbk, expects to complete the renovation construction projects in Saudi Arabia's Grand Mosque on time. Under the contract, the renovation is expected to be completed prior to the pilgrimage activities are expected to begin in late September.
"In the Grand Mosque we get contracts for work packages, which are located on one side of the pilgrims while performing sai (ritual jog)," said Head of Investor Relations Waskita, Agus Sugiono, the headline, Thursday, April 11, 2013.
The value of the work package, according to Agus, only about Rp70 billion. However, Clairvoyant expects to be worked on other projects at the center of worship for Muslims around the world.
The renovation work of the Holy Mosque, he continued, has a lot of packages, but it is done gradually. Because the process is always separate, considering the Hajj pilgrims.
In this project, Agus added, Clairvoyant still cooperating with Bin Laden Group. In this project, Clairvoyant act to subcontractors.
Working closely with the Bin Laden Group, according to Agus, the company's strategy is to consider the risk of the tender, the availability of local materials, local banks, and also guarantees.
Previously, Managing Director The company is, M Choliq, said the mosque renovation work will begin in the near future. Clairvoyant project was obtained, according to him, will be done gradually in the long term of 5-10 years.
sources:
http://bisnis.news.viva.co.id/news/read/404330-waskita-karya-garap-renovasi-masjidil-haram